Buying a home? 5 RERA rights every homebuyer should know on builder delays, advance payments and construction defects

Buying a home? 5 RERA rights every homebuyer should know on builder delays, advance payments and construction defects
Photo credit: Livemint
Advertisement

RERA gives homebuyers legal protection against excessive advance payments, delayed possession, unauthorised changes to property plans, construction defects and false advertising. Here are five rights buyers should know before purchasing a home.

RERA provides several protections against unfair practices and non-compliance by developers. (AI-generated image used for representational purpose.)
RERA provides several protections against unfair practices and non-compliance by developers. (AI-generated image used for representational purpose.)
Photo credit: Livemint

Buying a home involves more than checking the price, location and amenities. Homebuyers also need to understand the legal protections available if a builder delays possession, changes the promised layout or fails to deliver what was advertised. The Real Estate (Regulation and Development) Act, 2016, commonly known as RERA, lays down several obligations for developers and gives buyers remedies in specified circumstances.

The law covers issues ranging from advance payments and changes to approved plans to defects after possession and misleading advertisements. However, the availability of a remedy depends on the relevant provision, the facts of the case and applicable state rules.

Here are five RERA rights homebuyers should know before purchasing a property.

Advertisement

1. A builder cannot take more than 10% before the agreement for sale

Under Section 13 of RERA, a promoter cannot accept more than 10% of the cost of an apartment, plot or building as an advance payment or application fee without first entering into a written agreement for sale with the buyer and registering that agreement.

The provision is intended to ensure that buyers have a formal agreement setting out the terms of the transaction before paying a substantial part of the property's cost. The agreement for sale is expected to specify details such as the development work, payment schedule and date of possession.

2. You can seek a refund or interest if the builder delays possession

Section 18 of RERA provides remedies when a promoter fails to complete a project or give possession in accordance with the agreement for sale.

If a buyer chooses to withdraw because of such a failure, the promoter is liable to return the amount received, along with prescribed interest and applicable compensation under the Act. If the buyer chooses to remain in the project, the promoter must pay interest for every month of delay until possession is handed over.

Advertisement
Originally published by Livemint on Oct 13, 2026 Read the full article at livemint.com
Read original
About this page. Sisnoo is an aggregator. This article was imported from a publisher feed and may have been reformatted. Copyright remains with the original publisher, and the headline, image and any quoted text are used for attribution and indexing purposes. Source links are preserved on every item in the archive.
Share

Comments

0 comments

No comments yet — be the first.

Advertisement

More from Livemint

View source

Related