Muglin-Malekhu road upgrade work gathers pace

Muglin-Malekhu road upgrade work gathers pace
Photo credit: Khabarhub

KATHMANDU: Upgrading work on the western section of the Muglin-Nagdhunga Road Project, from Muglin to Malekhu, is progressing rapidly.

Construction work has gained momentum with improvements in weather conditions. The 38.86-kilometre section is being upgraded with a concessional loan of Rs 4.8059 billion from the World Bank.

The contract for the road was awarded on December 30, 2022, with a completion deadline of three years. Around 55 percent of the work has been completed so far.

Photos: Hiralal Gurung/Nepal Photo Library

Photo credit: Khabarhub Photo credit: Khabarhub Photo credit: Khabarhub Photo credit: Khabarhub Photo credit: Khabarhub Photo credit: Khabarhub Photo credit: Khabarhub Photo credit: Khabarhub Photo credit: Khabarhub Photo credit: Khabarhub Photo credit: Khabarhub Photo credit: Khabarhub Photo credit: Khabarhub Photo credit: Khabarhub

Originally published by Khabarhub on Oct 5, 2026 Read the full article at english.khabarhub.com
Read original
About this page. Sisnoo is an aggregator. This article was imported from a publisher feed and may have been reformatted. Copyright remains with the original publisher, and the headline, image and any quoted text are used for attribution and indexing purposes. Source links are preserved on every item in the archive.
Share

Comments

0 comments

No comments yet — be the first.

More from Khabarhub

View source

Related